日韩hdI久操天堂I久草在线费播放视频I依人做aI强开小受嫩苞第一次免费视频I鲁一鲁在线I亚洲淫小说AV在线I绿帽 无套 91 九色 论坛I大香焦超碰I国产96视频I久久免费的精品国产v∧I五月天婷婷综合I可以免费看av的网站I欧洲精品码一区二区三区免费看I日本二三四区I日韩黄色一级电影I99爱精品视频在线观看I特级西西www44高清大胆图片

How to Construction HDPE Double Wall Corrugated Pipe

2025-03-19

How to Construction HDPE Double Wall Corrugated Pipethe1page

before excavating the pipeline trench, conduct a comprehensive understanding of the geological conditions of the construction site, groundwater conditions, and design requirements of the rain and sewage system, and reasonably determine the buried depth of the pipeline and the treatment method of the foundation. Among them, the most important work is to verify the bearing capacity of the foundation foundation. If it does not meet the construction requirements, it should be dealt with through measures such as replacement and stone throwing to improve the bearing capacity of the foundation. After preparing for construction, the trench should be mined according to the pipeline construction plan. The geometric dimensions of the trench should conform to the design plan. If there are loose stones and earth blocks at the bottom of the trench, it should be removed, and a sand cushion should be laid on it to compact and level, so as to avoid hard objects from damaging the Wuhan HDPE double-wall corrugated pipe.

2. Install

to install the HDPE double-wall corrugated pipe. Review the depth, width, and bottom standard of the trench. After confirming that there is no gravel, broken soil, etc. in the trench, the installation work is officially started. HDPE double-wall corrugated pipe itself is not of high quality. Generally, large-scale hoisting devices are not required. If the buried depth of the pipeline is less than 3.0m and the diameter is lower than DN500, the lower pipe can be manually used. If the buried depth of the pipeline is higher than 3.0m and the diameter is higher than DN500, the hoisting installation method needs to be adopted. When hoisting and installing, the pipeline should be smooth when it is lowered to the bottom of the trench and cannot disturb the foundation. When it is necessary to cut the pipeline, the pipeline section should be vertical and flat, and the pipeline itself cannot be damaged. When installing, pay attention to the following points: First, the pipeline should be laid in a straight line. If it needs to be laid in a folded line, the relative corner should not be greater than 2; Second, after the pipeline is lowered, the drainage in the groove should be good, and there should be no water accumulation to prevent electric shock accidents; Third, the interface between the pipe and the pipe should leave a certain space to facilitate subsequent connection.

Third, the connection methods of connecting

HDPE double-wall corrugated pipe mainly include heat shrinkage sleeve connection, electric hot melt belt connection, etc., and their respective operation points are different. In the heat shrinkage sleeve connection method, first clean up the moisture and debris on the surface of the pipe, use the heat shrinkage belt to tightly wrap the pipe joint part, and use a flame gun to slightly bake the heat shrinkage belt and the pipe contact part. After that, wrap the baked heat shrinkable tape with another heat shrinkable tape, clamp it tightly, and then bake it with a flame gun at the part where the heat shrinkable tape is wrapped, first up and down, then left and right, so that the heat shrinkable tape is completely close to the pipe. In the connection mode of the electric hot melt belt, the surface of the pipe should also be cleaned first, the joint part should be wrapped with the electric hot melt belt, and the buckle belt should be fastened. Connect the electric hot melt belt to the electric hot melt machine, set the current intensity and heating time. After the electric hot melt is completed, fasten the buckle belt again and cool for a period of time. After checking that the connection quality meets the standard requirements, release the buckle belt. In addition to the connection between the pipe and the pipe, the connection between the Wuhan

Jingjie HDPE double-wall corrugated pipe and the well should also be paid attention to. HDPE double-wall corrugated pipe first goes deep into the well from the pipe trench, and the pipe is propped up with a support device to prevent concentrated load or shearing. Common way of connecting HDPE double-wall corrugated pipe with the well wall: Apply polyvinyl chloride adhesive at the connection between HDPE double-wall corrugated pipe and the well wall, lay a layer of fine sand on it, penetrate the pipe into the well wall, and use cement mortar to build and block.

4. Water closure test

After the pipeline is connected, conduct a water closure test to confirm whether the tightness of the pipeline in the water injection situation meets the requirements. First, check whether there is blockage, water accumulation, etc., inside the pipeline. After confirming that there is no above situation, inject water into the pipeline. After water injection, keep it for a period of time. If the scale of the pipeline project is large and it is impossible to implement the closed water test one by one, the closed water test pipeline can be determined by sampling. If water seepage or leakage is found, the test should be stopped immediately, the pipeline connection should be re-carried out, and the closed water test should be carried out again.

Fifth, backfill

After completing the above work, start the backfill work. Backfill from the connection part of the pipeline and the foundation first. The method adopts a symmetrical form. It is forbidden to backfill on one side and then backfill on the other side. The symmetrical method is also used for tamping to reduce the impact on the pipeline and avoid the deformation of the pipeline. When backfilling, a layered filling method is used, and the thickness of each layer of backfill soil is controlled between 0.15m and 0.20m. The thickness of the backfill soil layer at the top of the pipeline is about 0. If conditions permit, mechanical rolling can be used to ensure that the compaction of the backfill meets the design requirements.

This article is reproduced on the Internet and is only used for technical research and sharing. If there is any infringement, please contact us to delete it. Wuhan corrugated pipe, Hubei double-wall corrugated pipe, AD pe double-wall corrugated pipe, Jingjie HDPE double-wall corrugated pipe, Yonggao corrugated pipe can contact us.


主站蜘蛛池模板: 麻豆传传媒久久久爱| 免费 黄 色 人成 视频 在 线| 国产亚洲欧美日韩俺去了| 亚洲国产精品久久久久久久| 国产女同疯狂作爱系列| 男人扒开女人腿桶到爽免费| 97成人碰碰久久人人超级碰oo| 国产乱辈通伦影片在线播放亚洲| 57pao成人国产永久免费视频| 国产人妻久久精品二区三区| 亚洲一区二区色情苍井空| 丝袜无码专区人妻视频| 一本一道波多野结衣av中文| 四虎永久在线高清国产精品| 免费无码av片在线观看中文| 国产成人无码av在线播放dvd| 国产成+人+综合+亚洲欧美| 久久久久久国产精品美女| 自拍偷在线精品自拍偷无码专区| 国产色视频一区二区三区| 亚洲人和日本人jzz视频| 99热成人精品热久久6网站| 四虎影成人精品a片| 不卡无在一区二区三区四区| 亚洲色帝国综合婷婷久久 | 青青青国产精品国产精品美女| 国产精品久久无码不卡黑寡妇| 老熟妇高潮一区二区三区| 国产精品人成视频国模| 无码av中文一区二区三区桃花岛| 日韩制服国产精品一区| 无套无码孕妇啪啪| 2020精品国产自在现线看| 人人添人人妻人人爽夜欢视av| 亚洲a∨无码一区二区| 国产亚洲精品线视频在线| 少妇呻吟白浆高潮啪啪69| 色播在线精品一区二区三区四区| 亚洲精品无人区| 国产成人无码网站| 日本在线观看|